Addenbrookes roundabout works 11
Here is the latest update on our safety improvement works at Addenbrooke’s roundabout.
Over the past week the team have completed excavations between Fendon Road and Hills Road, marking an important milestone in this phase of work. Tactile paving installation is underway, and drainage and gully installations are progressing, while kerb and edging works are now 85% complete. Ducting installation also continues on schedule.
The temporary traffic signals are still in place and are effectively managing traffic flow, with no issues being reported. Traffic management continues to be in place overnight to maintain the site team’s safety and is removed during daylight hours to allow traffic to use the roundabout normally.
Looking ahead, the focus will be on completing the new kerb line installations and finishing the drainage system. With major excavation works complete and supporting infrastructure well advanced, the project remains on track for its next stages.
Related Blog
Blog
City Council Report July 2026
Council Following the elections the City Council is now made up of the following parties: 17 Labour 12 Green 11 Liberal Democrat 1 Conservat…
Read more →
Blog
COUNTY COUNCIL and GCP REPORT JULY 2026
In this report: Makeup of Full Council following by-election Local Government Reorganisation Children and Young people - Holiday activities…
Read more →
Blog
Cambridge South Station Opening
The Cambridge South train station opens on Sunday. I wanted to let you know about the traffic monitoring that will be done by the Campus to…
Read more →
Join the conversation