Addenbrookes roundabout update 20
We reached an important milestone for the project this week, as the team installed the last street-lighting column on the site which allowed them to also complete the final area of asphalting.
The only remaining task is to complete the commissioning of the permanent traffic lights. To ensure all safety aspects are fully met, a joint approach with the Cambridgeshire County Council’s signals team has been agreed, allowing the transfer and testing of the signals to take place simultaneously next week. So the commissioning of the new signalling system is now provisionally scheduled for 25–26 November, with the temporary signal system to be decommissioned on 27–28 November.
The traffic-management arrangements will continue to be monitored closely during this period to ensure the safe movement of all roundabout users, which is why the temporary signals will remain until we are happy the permanent signal installation is fully completed and commissioned.
Related Blog
Blog
City Council monthly update November 2026
Council Councillors heard a petition signed by 1,900 people on Cambridge’s Growth, calling for a review of the impact of major developments…
Read more →
Blog
County Council Monthly Report November 2026
LOCAL GOVERNMENT REORGANISATION The Government announced at the end of October that it has still not made up its mind about new council boun…
Read more →
Blog
LGR
5 new decisions were made on LGR today. None related to Cambridgeshire and Peterborough so we are still waiting locally for a decision. The…
Read more →
Join the conversation
Comments are closed for this post.