During this last week, the team have been working on:

β€’ Kerb line works: Excavation and installation of the new kerb line, following the removal of the existing kerb line.

β€’ Crossing point improvements: Installation of a new crossing point at the Fendon Road junction, including installing a new traffic signal pole and tactile paving.

β€’ Shared footway surfacing: Asphalt installation for the new shared footway is planned for the end of this week and will continue next week, subject to weather conditions.

They will continue to monitor conditions closely to minimise disruption, and we appreciate your patience and cooperation while these essential works are delivered.

Join the conversation

Comments are closed for this post.

Keep reading

Related Blog

Eddeva Development Blog
πŸ“… 6 Oct 2026

Eddeva Development

I was at the Eddeva development today to hear about progress on the site. I got taken round and shown the progress. Some information about t…

Read more β†’