Work is continuing to improve safety for all road users at Addenbrooke’s roundabout.
Last week, the site team worked specifically on two tasks. They prepared for the installation and commissioning of upgraded traffic signals which involved the fitting of new ducts and sockets while they continued to widen the carriageway by shrinking the central island.
This week, the team will be installing permanent poles for the new signals; the temporary traffic lights will remain on site until 11 June, when they will be fully decommissioned and removed. The permanent traffic lights will be switched back on the same day.
The team will also continue work on widening the carriageway.
We are pleased that the programme remains on target to be completed within the allotted eight weeks.
Also in response to a question I can confirm all traffic management equipment is removed during daylight hours, with the exception of cones on the newly-widened carriageway area. This does not impede the flow of traffic but protects the area the site team has worked on to date.
Related Blog
Blog
Eddeva Development
I was at the Eddeva development today to hear about progress on the site. I got taken round and shown the progress. Some information about t…
Read more →
Blog
City Council Monthly Report October 2026
In this report: Planning 25/04382/FUL and 25/04383/LBC Market Square 25/04484/FUL 87-93 Oxford Road and Fitzwilliam College Sportsground 25/…
Read more →
Blog
County Council Monthly report October 2026
In this report: LGR STRATEGY, RESOURCES AND PERFORMANCE Quality of Life Council budget consultation ADULTS & HEALTH Tackling obesity CHILDRE…
Read more →
Join the conversation
Comments are closed for this post.