Fence barriers have been installed, and all white lining and asphalting works are completed. Snagging corrections are being addressed as part of the final quality checks.
Traffic signal installation continues to advance. We are scheduled to connect the permanent signals and remove the temporary system next week, with the new signals expected to go live during this week (w/c 17 November). Over the coming days, we will also be installing the streetlighting columns, and permanent traffic signals which are expected to go live on Tuesday 18 November. The temporary signals will then be decommissioned on 20 and 21 November.
We also have a small section of additional resurfacing planned this week and the installation of the memorial bike Sheffield stand.
We continue to work hard to minimise disruption while progressing the project safely.
Related Blog
Blog
City Council Report July 2026
Council Following the elections the City Council is now made up of the following parties: 17 Labour 12 Green 11 Liberal Democrat 1 Conservat…
Read more →
Blog
COUNTY COUNCIL and GCP REPORT JULY 2026
In this report: Makeup of Full Council following by-election Local Government Reorganisation Children and Young people - Holiday activities…
Read more →
Blog
Cambridge South Station Opening
The Cambridge South train station opens on Sunday. I wanted to let you know about the traffic monitoring that will be done by the Campus to…
Read more →
Join the conversation