Addenbrookes Roundabout Update 19
This is the latest update to the roadworks at Addenbrookes roundabout.
Fence barriers have been installed, and all white lining and asphalting works are completed. Snagging corrections are being addressed as part of the final quality checks.
Traffic signal installation continues to advance. We are scheduled to connect the permanent signals and remove the temporary system next week, with the new signals expected to go live during this week (w/c 17 November). Over the coming days, we will also be installing the streetlighting columns, and permanent traffic signals which are expected to go live on Tuesday 18 November. The temporary signals will then be decommissioned on 20 and 21 November.
We also have a small section of additional resurfacing planned this week and the installation of the memorial bike Sheffield stand.
We continue to work hard to minimise disruption while progressing the project safely.
Related Blog
Blog
City Council monthly update November 2026
Council Councillors heard a petition signed by 1,900 people on Cambridge’s Growth, calling for a review of the impact of major developments…
Read more →
Blog
County Council Monthly Report November 2026
LOCAL GOVERNMENT REORGANISATION The Government announced at the end of October that it has still not made up its mind about new council boun…
Read more →
Blog
LGR
5 new decisions were made on LGR today. None related to Cambridgeshire and Peterborough so we are still waiting locally for a decision. The…
Read more →
Join the conversation
Comments are closed for this post.